10/02/2006
Chester Township Public Schools
Black River – Bragg - Dickerson
Weekly Update
Activities of the last week:
Black River Middle School
- Completed layout and installation for building addition floor slab
- Commenced installation of ceiling grid – Media Center
- Continued electrical for renovation area’s
- Continued installation of building addition gas line
Bragg Elementary School
- Continued exterior site work for building addition
- Continued rough / finish interior-exterior electric
- Continued new addition foundation layout and installation
Dickerson Elementary School
- Continued rough interior / exterior electric
- Continued installation of new gas lines for additions
- Continued layout and installation of site piping for building sprinkler system
- Continued site-work for drainage field
- Completed under slab rough plumbing for “K” addition
- Completed building addition back-fill and gravel base for K addition
- Continued installation of new gym foundations
Scheduled Activities for the week of October 02– October 6, 2006
Overall Project:
Black River Middle School
- Commence layout and installation of masonry walls for new building addition
- Commence installation of Media Center carpet
- Continue installation of Media Center ceiling
- Continue corridor floor tile patch / tile
- Continue Media Center HVAC system installation
Bragg Elementary School
- Continue relocation of building electrical service
- Continue new addition building foundation layout and installation
- Continue site work – installation of storm sewer piping
Dickerson Elementary School
- Continue site-work for parking, roadway and drainage field
- Continue installation of gas piping for new additions
- Commence installation of building steel for “K” wing addition
- Continue interior / exterior electrical
- Continue foundation layout and installation for Gym
Impact to Students & Staff:
Noise:
- Truck traffic and large machinery on site loading and unloading
Traffic and Parking:
- Construction contractor parking is designated to the rear parking, not near pool parking (Black River).
- Bragg and Dickerson parking lots have limited parking and revised traffic patterns, due to extensive site construction.
- Construction traffic and deliveries will be limited during morning drop-off and afternoon pick-up.
Cleanup:
- Contractors were told to pick up any debris in the area.
- Roadways will have to be kept clean in front of school and nearby roads.

Black River Middle School – New addition floor slab

Dickerson Elementary School – Gym wall foundation

Dickerson Elementary School – New Gym foundation

Dickerson Elementary School – Building Addition slab gravel base

Bragg Elementary School – Building Addition Foundations

Bragg Elementary School – New addition foundation forms

Dickerson Elementary School – Drainage Field