10/02/2006

Chester Township Public Schools

Black River – Bragg - Dickerson

Weekly Update

Activities of the last week:
Black River Middle School

  • Completed layout and installation for building addition floor slab
  • Commenced installation of ceiling grid – Media Center
  • Continued electrical for renovation area’s
  • Continued installation of building addition gas line

Bragg Elementary School  

  • Continued exterior site work for building addition
  • Continued rough / finish interior-exterior electric
  • Continued new addition foundation layout and installation

Dickerson Elementary School

  • Continued rough interior / exterior electric
  • Continued installation of new gas lines for additions
  • Continued layout and installation of site piping for building sprinkler system
  • Continued site-work for drainage field
  • Completed under slab rough plumbing for “K” addition
  • Completed building addition back-fill and gravel base for K addition
  • Continued installation of new gym foundations

Scheduled Activities for the week of October 02– October 6, 2006
Overall Project:
Black River Middle School

  • Commence layout and installation of masonry walls for new building addition
  • Commence installation of Media Center carpet
  • Continue installation of Media Center ceiling
  • Continue corridor floor tile patch / tile
  • Continue Media Center HVAC system installation

Bragg Elementary School

  • Continue relocation of building electrical service
  • Continue new addition building foundation layout and installation
  • Continue site work – installation of storm sewer piping

 

Dickerson Elementary School

  • Continue site-work for parking, roadway and drainage field
  • Continue installation of gas piping for new additions
  • Commence installation of building steel for “K” wing addition
  • Continue interior / exterior electrical
  • Continue foundation layout and installation for Gym

 

Impact to Students & Staff:

Noise: 

  • Truck traffic and large machinery on site loading and unloading

 

Traffic and Parking:

    • Construction contractor parking is designated to the rear parking, not near pool parking (Black River).
    • Bragg and Dickerson parking lots have limited parking and revised traffic patterns, due to extensive site construction.
    • Construction traffic and deliveries will be limited during morning drop-off and afternoon pick-up.

Cleanup:

  • Contractors were told to pick up any debris in the area.
  • Roadways will have to be kept clean in front of school and nearby roads.

 

 

                                           

Black River Middle School – New addition floor slab

 

 


Dickerson Elementary School – Gym wall foundation

 


Dickerson Elementary School – New Gym foundation

 


Dickerson Elementary School – Building Addition slab gravel base

 


Bragg Elementary School – Building Addition Foundations

Bragg Elementary School – New addition foundation forms

 


Dickerson Elementary School – Drainage Field