10/09/2006

Chester Township Public Schools

Black River – Bragg - Dickerson

Weekly Update

Activities of the last week:
Black River Middle School

  • Completed layout and installation for building addition floor slab
  • Continued installation of ceiling grid – Media Center
  • Continued electrical for renovation area’s – Media Center lighting
  • Continued installation of new addition plumbing – bathroom rough-in
  • Commenced masonry wall installation – new addition

Bragg Elementary School  

  • Continued exterior site work for building addition
  • Continued rough / finish interior-exterior electric
  • Completed new addition foundation layout and installation
  • Completed carpet installation – new Media Center

Dickerson Elementary School

  • Continued rough interior / exterior electric
  • Completed installation of new gas lines for additions
  • Continued layout and installation of site piping for building sprinkler system
  • Continued site-work for drainage field
  • Completed installation of structural steel for “K” addition
  • Commenced prep-work for concrete floor installation - K addition
  • Continued installation of new gym foundations

Scheduled Activities for the week of October 09– October 13, 2006
Overall Project:
Black River Middle School

  • Continue layout and installation of masonry walls for new building addition
  • Commence installation of Media Center carpet
  • Continue installation of Media Center ceiling
  • Continue corridor floor tile patch / tile
  • Continue Media Center lighting installation

Bragg Elementary School

  • Continue relocation of building electrical service
  • Commence layout and grading of new courtyard
  • Continue site work and building foundation back-fill
  • Commence layout and installation of underground plumbing – new addition

Dickerson Elementary School

  • Continue site-work for parking, roadway and drainage field
  • Continue layout and installation – concrete floor – K wing
  • Commence bathroom layout / rough-in for bathrooms – K wing
  • Continue interior / exterior electrical
  • Continue foundation layout and installation for Gym

 

Impact to Students & Staff:

Noise: 

  • Truck traffic and large machinery on site loading and unloading

 

Traffic and Parking:

    • Construction contractor parking is designated to the rear parking, not near pool parking (Black River).
    • Bragg and Dickerson parking lots have limited parking and revised traffic patterns, due to extensive site construction.
    • Construction traffic and deliveries will be limited during morning drop-off and afternoon pick-up.

Cleanup:

  • Contractors were told to pick up any debris in the area.
  • Roadways will have to be kept clean in front of school and nearby roads.

                                          

Black River Middle School – Masonry wall installation – New addition

 


Black River Middle School – Plumbing rough-in for new bathroom(s)


Black River Middle School – Media Center ceiling and lighting installation

 


Dickerson Elementary School – Gym wall foundation

 


Dickerson Elementary School – Installation of new HVAC unit for Nurse’s suite

 


Dickerson Elementary School – Building steel installation – K wing

 


Bragg Elementary School – Building Addition Foundations


Bragg Elementary School – New addition foundation