10/23/2006
Chester Township Public Schools
Black River – Bragg - Dickerson
Weekly Update
Activities of the last week:
Black River Middle School
- Continued installation of electrical – New Addition
- Completed installation of ceiling tile – Media Center
- Commenced – installation of ductwork – New Addition
- Continued installation of new addition plumbing – bathroom rough-in
- Continued masonry/brick wall installation – new addition
Bragg Elementary School
- Continued exterior site work for building addition
- Continued rough / finish interior-exterior electric
- Continued grading and sidewalks for new courtyard
- Completed installation underground plumbing – new addition
- Commenced foundation back-fill – New Addition
Dickerson Elementary School
- Continued rough interior / exterior electric
- Continue site-work for parking, roadway and drainage field
- Completed installation of concrete floor – K addition
- Commenced bathroom rough-out for bathrooms – K addition
- Continued site-work for drainage field
- Commenced masonry wall layout - K addition
- Continued installation of new gym foundations
Scheduled Activities for the week of October 23– October 27, 2006
Overall Project:
Black River Middle School
- Continue layout and installation of masonry walls for new building addition
- Commence installation of Media Center fixtures and furniture
- Continue installation of Electric / Plumbing / HVAC for new addition
- Continue installation of ductwork for new building addition
Bragg Elementary School
- Continue relocation of building electrical service
- Continue layout and grading of new courtyard
- Continue site work and building addition slab pre-work
- Commence installation of building steel – new addition
- Commence installation of Media Center fixtures and furniture
Dickerson Elementary School
- Continue site-work for parking, roadway and drainage field
- Continue layout and installation – masonry walls – K wing
- Commence bathroom layout / rough-in for bathrooms – K wing
- Continue interior / exterior electrical
- Continue foundation layout and installation for Gym
Impact to Students & Staff:
Noise:
- Truck traffic and large machinery on site loading and unloading
Traffic and Parking:
- Construction contractor parking is designated to the rear parking, not near pool parking (Black River).
- Bragg and Dickerson parking lots have limited parking and revised traffic patterns, due to extensive site construction.
- Construction traffic and deliveries will be limited during morning drop-off and afternoon pick-up.
Cleanup:
- Contractors were told to pick up any debris in the area.
- Roadways will have to be kept clean in front of school and nearby roads.

Black River Middle School – interior construction – New addition

Black River Middle School – Interior construction – New Addition

Black River Middle School – Media Center interior

Dickerson Elementary School – Concrete floor installation – K wing

Dickerson Elementary School – Interior construction – K wing

Dickerson Elementary School – Foundations for Gym addition

Dickerson Elementary School – Gym foundation installation

Bragg Elementary School – Courtyard walk-way installation