10/23/2006

Chester Township Public Schools

Black River – Bragg - Dickerson

Weekly Update

Activities of the last week:
Black River Middle School

  • Continued installation of electrical – New Addition
  • Completed installation of ceiling tile – Media Center
  • Commenced – installation of ductwork – New Addition
  • Continued installation of new addition plumbing – bathroom rough-in
  • Continued masonry/brick wall installation – new addition

Bragg Elementary School  

  • Continued exterior site work for building addition
  • Continued rough / finish interior-exterior electric
  • Continued grading and sidewalks for new courtyard
  • Completed installation underground plumbing – new addition
  • Commenced foundation back-fill – New Addition

Dickerson Elementary School

  • Continued rough interior / exterior electric
  • Continue site-work for parking, roadway and drainage field
  • Completed installation of concrete floor – K addition
  • Commenced bathroom rough-out for bathrooms – K addition
  • Continued site-work for drainage field
  • Commenced masonry wall layout - K addition
  • Continued installation of new gym foundations

Scheduled Activities for the week of October 23– October 27, 2006
Overall Project:
Black River Middle School

  • Continue layout and installation of masonry walls for new building addition
  • Commence installation of Media Center fixtures and furniture
  • Continue installation of Electric / Plumbing / HVAC for new addition
  • Continue installation of ductwork for new building addition

Bragg Elementary School

  • Continue relocation of building electrical service
  • Continue layout and grading of new courtyard
  • Continue site work and building addition slab pre-work
  • Commence installation of building steel – new addition
  • Commence installation of Media Center fixtures and furniture

Dickerson Elementary School

  • Continue site-work for parking, roadway and drainage field
  • Continue layout and installation – masonry walls – K wing
  • Commence bathroom layout / rough-in for bathrooms – K wing
  • Continue interior / exterior electrical
  • Continue foundation layout and installation for Gym

 

Impact to Students & Staff:

Noise: 

  • Truck traffic and large machinery on site loading and unloading

 

Traffic and Parking:

    • Construction contractor parking is designated to the rear parking, not near pool parking (Black River).
    • Bragg and Dickerson parking lots have limited parking and revised traffic patterns, due to extensive site construction.
    • Construction traffic and deliveries will be limited during morning drop-off and afternoon pick-up.

Cleanup:

  • Contractors were told to pick up any debris in the area.
  • Roadways will have to be kept clean in front of school and nearby roads.

                                          

Black River Middle School – interior construction – New addition

 


Black River Middle School – Interior construction – New Addition


Black River Middle School – Media Center interior

 


Dickerson Elementary School – Concrete floor installation – K wing

 


Dickerson Elementary School – Interior construction – K wing


Dickerson Elementary School – Foundations for Gym addition

 


Dickerson Elementary School – Gym foundation installation

 


Bragg Elementary School – Courtyard walk-way installation