Activities of the last week:
Black River Middle School
- Continued installation of electrical – New Addition
- Continued installation of new roof- New addition
- Continued replacement of exterior windows RM#12,14,16
- Continued installation of new addition plumbing – bathroom / science rough-in
- Continued masonry/brick wall installation – new addition
- Commenced installation of HVAC units – new addition
Bragg Elementary School
- Continued exterior site work for building addition
- Continued fixture installation – Media Center
- Continued structural steel – New Addition
Dickerson Elementary School
- Continued rough interior / exterior electric
- Continued installation of masonry / brick walls – K addition
- Continued bathroom rough-out for bathrooms – K addition
- Continued installation of new gym foundations
Scheduled Activities for the week of November 20– November 24, 2006
Overall Project:
Black River Middle School
- Continue layout and installation of masonry / brick walls for new building addition
- Continue installation of Electric / Plumbing / HVAC for new addition
- Continue installation of HVAC units for new building addition
- Continue installation of new roof for new addition
Bragg Elementary School
- Commence exterior masonry wall layout and installation – new addition
- Continue structural steel installation
- Continue site-work for parking, roadway and drainage
- Continue installation of Media Center fixtures and furniture
Dickerson Elementary School
- Continue site-work for parking, roadway and drainage field
- Continue layout and installation – masonry walls / brick – K wing
- Continue bathroom layout / rough-in for bathrooms – K wing
- Continue interior / exterior electrical
- Continue foundation layout and installation for Gym
- Commence new roof layout and installation – K wing
Impact to Students & Staff:
Noise:
- Truck traffic and large machinery on site loading and unloading
Traffic and Parking:
- Construction contractor parking is designated to the rear parking, not near pool parking (Black River).
- Bragg and Dickerson parking lots have limited parking and revised traffic patterns, due to extensive site construction.
- Construction traffic and deliveries will be limited during morning drop-off and afternoon pick-up.
Cleanup:
- Contractors were told to pick up any debris in the area.
- Roadways will have to be kept clean in front of school and nearby roads.

Black River Middle School – Roof / HVAC unit installation – new addition

Black River Middle School – Exterior brick installation – new addition

Black River Middle School – Exterior brick installation – new addition

Dickerson Elementary School – K wing corridor

Dickerson Elementary School – Exterior brick wall construction – K wing

Bragg Elementary School – Structural steel installation – new addition

Bragg Elementary School – Structural steel installation

Bragg Elementary School – Media Center - furniture

Bragg Elementary School – Media Center furniture