11/27/2006

Chester Township Public Schools

Black River – Bragg - Dickerson

Weekly Update

Activities of the last week:
Black River Middle School

  • Continued installation of electrical – New Addition
  • Commence installation of exterior windows- New addition
  • Completed interior masonry walls – New addition
  • Continued installation of new addition plumbing – bathroom / science rough-in
  • Continued brick wall installation – new addition
  • Continue installation of HVAC units – new addition

Bragg Elementary School  

  • Commence floor slab prep New addition
  • Continued fixture installation – Media Center
  • Completed structural steel – New addition
  • Commence exterior masonry wall – New addition

Dickerson Elementary School

  • Continued rough interior / exterior electric
  • Continued installation of masonry / brick walls – K addition
  • Continued bathroom rough-out for bathrooms – K addition
  • Continued installation of new gym foundations
  • Commence installation of road curbing

Scheduled Activities for the week of November 27– December 01, 2006
Overall Project:
Black River Middle School

  • Continue layout and installation of brick walls for new building addition
  • Continue installation of Electric / Plumbing / HVAC for new addition
  • Continue installation of HVAC units for new building addition
  • Continue installation of new roof for new addition
  • Commence sidewalk / curb layout for new addition

Bragg Elementary School

  • Continue exterior masonry wall layout and installation – new addition
  • Continue floor slab layout and installation – new addition
  • Continue site-work for parking, roadway and drainage
  • Continue installation of Media Center fixtures and furniture

Dickerson Elementary School

  • Continue site-work for parking, roadway and drainage field
  • Continue layout and installation – masonry walls / brick – K wing
  • Continue bathroom layout / rough-in for bathrooms – K wing
  • Continue interior / exterior electrical
  • Continue foundation layout and installation for Gym
  • Commence new roof layout and installation – K wing

 

 

Impact to Students & Staff:

Noise: 

  • Truck traffic and large machinery on site loading and unloading

 

Traffic and Parking:

    • Construction contractor parking is designated to the rear parking, not near pool parking (Black River).
    • Bragg and Dickerson parking lots have limited parking and revised traffic patterns, due to extensive site construction.
    • Construction traffic and deliveries will be limited during morning drop-off and afternoon pick-up.

Cleanup:

  • Contractors were told to pick up any debris in the area.
  • Roadways will have to be kept clean in front of school and nearby roads.

 

 

                                          

Black River Middle School – Exterior elevation – new addition

 


Black River Middle School – Exterior brick installation – new addition

 


Dickerson Elementary School – Exterior Elevation – K wing

 


Dickerson Elementary School – Foundations for Gym canopy

 


Bragg Elementary School – Sample wall for new addition

 


Bragg Elementary School – Floor slab prep / exterior walls- New addition

 


Bragg Elementary School – New addition

Bragg / Dickerson Elementary School – Road curbing installation