12/04/2006
Chester Township Public Schools
Black River – Bragg - Dickerson
Weekly Update
Activities of the last week:
Black River Middle School
- Continued installation of electrical – New Addition
- Completed installation of exterior windows- New addition
- Commence layout / installation of curbs and sidewalks – New addition
- Continued installation of new addition plumbing – bathroom / science rough-in
- Completed brick wall installation – new addition
- Continue installation of HVAC units – new addition
Bragg Elementary School
- Completed floor slab installation- New addition
- Commence product return (books) – Media Center
- Commence HVAC installation – New addition
- Continued exterior masonry wall – New addition
Dickerson Elementary School
- Continued rough interior / exterior electric
- Continued installation of masonry / brick walls – K addition / Gym
- Commence HVAC unit(s) and ductwork installation – K addition
- Continued installation of new gym foundations
- Commence underground plumbing installation – Gym addition
- Commence layout and installation of roofing – K addition
Scheduled Activities for the week of December 04– 08, 2006
Overall Project:
Black River Middle School
- Commence installation of interior soffits and finishes
- Continue installation of Electric / Plumbing / HVAC for new addition
- Continue installation of HVAC units for new building addition
- Continue installation of new roof for new addition
- Continue sidewalk / curb layout for new addition
Bragg Elementary School
- Continue exterior masonry wall layout and installation – new addition
- Commence above ground plumbing rough-in – New addition
- Commence electrical conduit installation – New addition
- Continue site-work for parking, roadway and drainage
- Continue HVAC installation (piping / Hangers) – New Addition
Dickerson Elementary School
- Continue site-work for parking, roadway and drainage field
- Continue layout and installation – masonry walls / brick – K wing
- Continue interior / exterior electrical – K wing
- Continue foundation layout and installation for Gym
- Commence new roof layout and installation – K wing
Impact to Students & Staff:
Noise:
- Truck traffic and large machinery on site loading and unloading
Traffic and Parking:
- Construction contractor parking is designated to the rear parking, not near pool parking (Black River).
- Bragg and Dickerson parking lots have limited parking and revised traffic patterns, due to extensive site construction.
- Construction traffic and deliveries will be limited during morning drop-off and afternoon pick-up.
Cleanup:
- Contractors were told to pick up any debris in the area.
- Roadways will have to be kept clean in front of school and nearby roads.

Black River Middle School – Exterior elevation – new addition

Black River Middle School – Curbing installation – new addition

Dickerson Elementary School – HVAC unit(s) installation – K wing

Dickerson Elementary School – Exterior Elevation K -wing

Dickerson Elementary School – Exterior elevation new addition

Bragg Elementary School – Floor slab installation - New addition

Bragg Elementary School – New addition

Bragg Elementary School – Interior (office area) – new addition

Bragg Elementary – Renovated Media Center