Jump to Main Content

12/11/2006

Chester Township Public Schools

Black River – Bragg - Dickerson

Weekly Update

Activities of the last week:
Black River Middle School

  • Continued installation of electrical – New Addition
  • Commence installation of ceramic tile- New addition bathroom’s
  • Commence priming interior walls – New addition
  • Continued installation of new addition plumbing – bathroom / science rough-in
  • Continue installation of HVAC units – new addition

Bragg Elementary School  

  • Commenced above slab plumbing rough-in - New addition
  • Completed renovation – Media Center
  • Continued HVAC installation – New addition
  • Continued exterior masonry wall – New addition

Dickerson Elementary School

  • Continued rough interior / exterior electric
  • Completed installation of masonry / brick walls – K addition
  • Continue HVAC unit(s) and ductwork installation – K addition
  • Commenced floor slab installation – corridor / bathrooms - Gym
  • Continued underground plumbing installation – Gym addition
  • Continued layout and installation of roofing – K addition

Scheduled Activities for the week of December 11– 15, 2006
Overall Project:
Black River Middle School

  • Commence installation of interior soffits and finishes
  • Continue installation of Electric / Plumbing / HVAC for new addition
  • Continue installation of HVAC units for new building addition
  • Continue installation of new roof for new addition
  • Commence installation of service road paving – New addition

Bragg Elementary School

  • Continue exterior masonry wall layout and installation – new addition
  • Continue above ground plumbing rough-in – New addition
  • Continue electrical conduit installation – New addition
  • Continue site-work for parking, roadway and drainage
  • Continue HVAC installation (piping / Hangers) – New Addition

Dickerson Elementary School

  • Continue site-work for parking, roadway and drainage field
  • Continue HVAC / Plumbing for new addition – K wing
  • Continue interior / exterior electrical – K wing
  • Commence structural steel installation for Gym
  • Continue new roof layout and installation – K wing

Impact to Students & Staff:

Noise: 

  • Truck traffic and large machinery on site loading and unloading

 

Traffic and Parking:

    • Construction contractor parking is designated to the rear parking, not near pool parking (Black River).
    • Bragg and Dickerson parking lots have limited parking and revised traffic patterns, due to extensive site construction.
    • Construction traffic and deliveries will be limited during morning drop-off and afternoon pick-up.

Cleanup:

  • Contractors were told to pick up any debris in the area.
  • Roadways will have to be kept clean in front of school and nearby roads.

                                          

Black River Middle School – Exterior elevation – new addition


Black River Middle School – Curbing / sidewalk installation – new addition

 


Black River Middle School – Bathroom tile installation – New addition

 


Black River Middle School – Priming interior walls – New addition (science room)

 


Dickerson Elementary School – Exterior elevation new addition – K wing

 


Dickerson Elementary School – Floor slab installation – Bathroom /
corridor - Gym

 


Bragg Elementary School – New addition


Bragg Elementary School – Interior new addition

 


Dickerson / Bragg Elementary – Installation of roadway gravel base