12/18/2006

Chester Township Public Schools

Black River – Bragg - Dickerson

Weekly Update

Activities of the last week:
Black River Middle School

  • Continued installation of electrical – New Addition
  • Completed installation of ceramic tile- New Addition bathroom’s
  • Continued painting interior walls – New addition
  • Commenced interior student locker soffit – New Addition
  • Completed service road paving
  • Commenced replacement of exterior soffit panels for gym

Bragg Elementary School  

  • Continued plumbing, HVAC and electrical rough-in - New addition
  • Commence roof blocking – New addition
  • Continued HVAC installation – New addition
  • Continued exterior masonry wall – New addition

Dickerson Elementary School

  • Continued rough interior electric, plumbing, HVAC – K wing
  • Commenced HVAC gas line installation – K addition
  • Commenced service road paving – Bragg / Dickerson
  • Commenced structural steel installation  - Gym
  • Continued underground plumbing installation – Gym addition
  • Completed installation of roofing – K addition

Scheduled Activities for the week of December 18– 22, 2006
Overall Project:
Black River Middle School

  • Continue installation of interior finishes (painting, epoxy floors)
  • Continue installation of Electric / Plumbing / HVAC for new addition
  • Commence student locker layout and installation for new building addition
  • Continue installation of new roof for new addition and soffit panels for gym
  • Commence furniture/fixture layout installation – New addition

Bragg Elementary School

  • Continue exterior masonry wall layout and installation – new addition
  • Continue above ground plumbing rough-in – New addition
  • Continue electrical conduit installation – New addition
  • Continue site-work for parking, roadway and drainage
  • Continue HVAC installation (piping / Hangers) – New Addition

Dickerson Elementary School

  • Continue site-work for parking, roadway and drainage field
  • Continue HVAC / Plumbing for new addition – K wing
  • Continue interior / exterior electrical – K wing
  • Continue structural steel installation for Gym
  • Commence exterior window installation – K wing

Impact to Students & Staff:

Noise: 

  • Truck traffic and large machinery on site loading and unloading

Traffic and Parking:

    • Construction contractor parking is designated to the rear parking, not near pool parking (Black River).
    • Bragg and Dickerson parking lots have limited parking and revised traffic patterns, due to extensive site construction.
    • Construction traffic and deliveries will be limited during morning drop-off and afternoon pick-up.

Cleanup:

  • Contractors were told to pick up any debris in the area.
  • Roadways will have to be kept clean in front of school and nearby roads.

                                          

Black River Middle School – Exterior elevation – new addition

 


Black River Middle School – Student locker area – new addition

 


Black River Middle School – Science room – New addition

 


Black River Middle School – Replacement of gym soffit panels

 


Dickerson Elementary School – Structural steel installation - Gym

 


Dickerson Elementary School – Classroom interior- Gym

 


Bragg Elementary School – Rough plumbing – new addition bathrooms


Bragg Elementary School – Exterior courtyard elevation- new addition


Dickerson / Bragg Elementary – Installation of roadway - asphalt base