Activities of the last week:

  • Continued interior demolition – Black River Middle School
  • Commenced survey and layout of new additions – Black River / Bragg / Dickerson

Scheduled Activities for the week of June 19– June 23, 2006

Overall Project:

 

  • Commence exterior site work for new addition – Black River Middle School
  • Commence exterior site work for new addition – Bragg / Dickerson
  • Commence footing and foundations for new addition – Black River Middle School
  • Commence interior demolition – Bragg / Dickerson
  • Continue interior demolition– Black River Middle School

 

Impact to Students & Staff:

Noise:

  • Truck traffic and large machinery on site loading and unloading

 

Traffic and Parking:

    • Construction contractor parking is designated to the front & rear parking, not near pool parking ( Black River).
    • Bragg and Dickerson parking lots are closed for public use, due to extensive site construction.

 

Cleanup:

  • Contractors were told to pick up any debris in the area.
  • Roadways will have to be kept clean in front of school and nearby roads.


Black River Middle School – Science Room demolition

Black River Middle School – Band Room demolition

     