6/27/2006
Chester Township Public Schools
Black River – Bragg - Dickerson
Weekly Update
Activities of the last week:
- Completed interior demolition – Black River Middle School
- Commenced interior / exterior plumbing – Black River Middle School
- Commenced survey and layout of new additions – Black River / Bragg / Dickerson
- Commenced exterior site work for new addition – Black River Middle School
Scheduled Activities for the week of June 26– June 30, 2006
Overall Project:
- Continue exterior site work for new addition – Black River Middle School
- Commence exterior site work for new addition – Bragg / Dickerson
- Commence footing and foundations for new addition – Black River Middle School
- Commence interior demolition – Bragg / Dickerson
- Commence interior wall framing– Black River Middle School
Impact to Students & Staff:
Noise:
- Truck traffic and large machinery on site loading and unloading
Traffic and Parking:
- Construction contractor parking is designated to the front & rear parking, not near pool parking ( Black River).
- Bragg and Dickerson parking lots are closed for public use, due to extensive site construction
Cleanup:
- Contractors were told to pick up any debris in the area.
- Roadways will have to be kept clean in front of school and nearby roads.
Black River Middle School – Rock removal – new addition sewer line
Black River Middle School – Media center demolition (glass wall)
Epic Management, Inc.