Jump to Main Content

6/27/2006

Chester Township Public Schools

Black River – Bragg - Dickerson

Weekly Update

Activities of the last week:

  • Completed interior demolition – Black River Middle School
  • Commenced interior / exterior plumbing – Black River Middle School
  • Commenced survey and layout of new additions – Black River / Bragg / Dickerson
  • Commenced exterior site work for new addition – Black River Middle School

Scheduled Activities for the week of June 26– June 30, 2006

Overall Project:

  • Continue exterior site work for new addition – Black River Middle School
  • Commence exterior site work for new addition – Bragg / Dickerson
  • Commence footing and foundations for new addition – Black River Middle School
  • Commence interior demolition – Bragg / Dickerson
  • Commence interior wall framing– Black River Middle School

Impact to Students & Staff:

Noise:

  1. Truck traffic and large machinery on site loading and unloading

Traffic and Parking:

  1. Construction contractor parking is designated to the front & rear parking, not near pool parking ( Black River).
  2. Bragg and Dickerson parking lots are closed for public use, due to extensive site construction

Cleanup:

  1. Contractors were told to pick up any debris in the area.
  2. Roadways will have to be kept clean in front of school and nearby roads.


Black River Middle School – Rock removal – new addition sewer line

Black River Middle School – Media center demolition (glass wall)

    Epic Management, Inc.