7/18/2006
Chester Township Public Schools
Black River – Bragg - Dickerson
Weekly Update
Activities of the last week:
- Commenced rough interior electrical – Bragg & Black River Middle School
- Continued interior / exterior plumbing – Black River Middle School
- Continued exterior site work for new addition – Black River Middle School
- Commenced interior wall framing – Black River Middle School
Scheduled Activities for the week of July 10– July 14, 2006
Overall Project:
- Continue exterior site work for new addition – Black River Middle School
- Commence footing and foundations for new addition – Black River Middle School
- Continue interior renovation layout – Bragg / Dickerson
- Continue interior / exterior plumbing - Dickerson
- Continue interior wall framing– Black River Middle School
- Continue interior electrical – Black River / Bragg / Dickerson
Impact to Students & Staff:
Noise:
- Truck traffic and large machinery on site loading and unloading
Traffic and Parking:
- Construction contractor parking is designated to the front & rear parking, not near pool parking ( Black River).
- Bragg and Dickerson parking lots are closed for public use, due to extensive site construction
Cleanup:
- Contractors were told to pick up any debris in the area.
- Roadways will have to be kept clean in front of school and nearby roads.
Black River Middle School – Installation of interior wall framing for Media Center
Black River Middle School – building addition foundations
Epic Management, Inc.