8/10/2006

Chester Township Public Schools

Black River – Bragg - Dickerson

Weekly Update

Activities of the last week:

Black River Middle School

  • Continued rough interior electrical
  • Continued interior wall framing (Science wing, vocal, computer lab and media center)
  • Commenced backfilling footings and foundations for new addition
  • Commenced HVAC ductwork installation (Media, Computer Lab, and Vocal)
  • Completed waterproofing addition foundation walls

Bragg Elementary School

  • Continued interior plumbing interior modifications for Faculty lounge
  • Continued exterior plumbing- exterior sewer relocation
  • Completed interior masonry walls- Media Center, Computer Lab, and Faculty Room
  • Continued rough interior electric

Dickerson Elementary School

  • Continued rough interior electric
  • Continued interior plumbing interior modifications for Nurse’s office
  • Continued exterior plumbing- exterior sewer relocation
  • Commenced interior walls for Nurse’s office
  • Commenced site-work for addition building pad

Scheduled Activities for the week of August 7– August 11, 2006

 

Overall Project:

Black River Middle School

  • Continue installation of HVAC ductwork- science wing
  • Commence interior underground plumbing for addition
  • Continue interior electrical – rough
  • Continue interior wall framing renovation area’s
  • Continue site-work > grading and foundation backfill

Bragg Elementary School

  • Continue interior electrical – Renovation area’s
  • Commence interior wall framing – Media Center
  • Commence HVAC ductwork for Faculty Room

Dickerson Elementary School

  • Continue site-work for additions and drainage field
  • Continue interior masonry walls for Nurse’s office
  • Continue relocation of exterior sanitary sewer lines
  • Commence HVAC ductwork for Main office and Nurse’s office
  • Commence relocation of building generator
  • Continue interior / exterior electrical

 

Impact to Students & Staff:

Noise:

  • Truck traffic and large machinery on site loading and unloading

Traffic and Parking:

    • Construction contractor parking is designated to the front & rear parking, not near pool parking ( Black River).
    • Bragg and Dickerson parking lots are closed for public use, due to extensive site construction

Cleanup:

  • Contractors were told to pick up any debris in the area.
  • Roadways will have to be kept clean in front of school and nearby roads.

Black River Middle School – Exterior foundations – Black Middle School

 

 

Black River Middle School – Interior wall framing – Science wing

Dickerson Elementary School – Site work for new addition

 

Dickerson Elementary School – Nurse’s office bathroom

 

Bragg Elementary School – Computer Lab

 

Bragg Elementary School – Media Center office and storage