8/16/2006
Chester Township Public Schools
Black River – Bragg - Dickerson
Weekly Update
Activities of the last week:
Black River Middle School
- Continued rough interior electrical – renovation area’s
- Continued interior wall framing (Science wing, vocal, computer lab and media center)
- Commenced sheetrock wall taping (Science wing)
- Continued HVAC ductwork installation (media, science wing and vocal)
- Commenced exterior(sewer) / interior (water lines) plumbing for building addition
Bragg Elementary School
- Commenced exterior site work for building addition
- Commenced interior wall framing and ceiling grid – Media Center and Computer Lab
- Continued rough / finish interior electric
Dickerson Elementary School
- Continued rough interior electric
- Commence relocation of building electrical service
- Continued interior plumbing
- Continued exterior plumbing- exterior sewer relocation
- Completed interior walls for Nurse’s office
- Continued site-work for addition building pad and drainage field
Scheduled Activities for the week of August 14 – August 18, 2006
Overall Project:
Black River Middle School
- Continue installation of HVAC ductwork- vocal and new science room
- Continue interior underground plumbing for addition
- Continue interior electrical – rough
- Continue interior window and wall framing in renovation area’s
- Commence interior painting
Bragg Elementary School
- Continue interior electrical – Renovation area’s
- Commence relocation of building electrical service
- Continue interior wall framing – Media Center
- Commence HVAC ductwork for Faculty Room
Dickerson Elementary School
- Continue site-work for additions and drainage field
- Commence ceramic wall tile and epoxy floor for Nurse’s restroom
- Continue relocation of exterior sanitary sewer lines
- Commence HVAC ductwork for Main office and Nurse’s office
- Continue relocation of building generator and fuel supply
- Continue interior / exterior electrical
Impact to Students & Staff:
Noise:
- Truck traffic and large machinery on site loading and unloading
Traffic and Parking:
- Construction contractor parking is designated to the front & rear parking, not near pool parking ( Black River).
- Bragg and Dickerson parking lots are closed for public use, due to extensive site construction
Cleanup:
- Contractors were told to pick up any debris in the area.
- Roadways will have to be kept clean in front of school and nearby roads.

Black River Middle School – Sanitary sewer within addition – Black Middle School

Black River Middle School – HVAC ductwork – Science wing

Dickerson Elementary School – Site work for new addition

Dickerson Elementary School – Exterior sewer line relocation

Bragg Elementary School – Media Center framing and ceiling grid

Bragg Elementary School – Exterior site work
Epic Management, Inc.