8/28/2006

Chester Township Public Schools

Black River – Bragg - Dickerson

Weekly Update

Activities of the last week:

Black River Middle School

  • Commenced light fixture installation – renovation area’s
  • Continued interior wall framing ( vocal and science room)
  • Continued interior painting, ceiling installation (Science wing)
  • Continued HVAC ductwork installation (media, science and vocal)
  • Completed interior glass installation
  • Commenced floor tile installation

Bragg Elementary School

  • Continued exterior site work for building addition
  • Commenced plumbing fixture installation – Teacher Lounge, Media Center
  • Continued interior wall framing and ceiling grid – Media Center and Computer Lab
  • Continued rough / finish interior-exterior electric
  • Commenced light fixture installation – Teacher Lounge
  • Continued interior painting (Teacher lounge / Computer Lab / Media Center)
  • Commenced floor tile installation (Teacher Lounge, Computer Lab)

Dickerson Elementary School

  • Continued rough interior / exterior electric
  • Continued relocation of building electrical service
  • Commenced plumbing fixtures – Nurses lounge
  • Completed exterior plumbing- exterior sewer relocation
  • Commenced ceiling installation – Main Office and Nurses Area
  • Continued site-work for addition building pad (gym) and drainage field
  • Continued installation of footing for K addition

Scheduled Activities for the week of August 28– September 01, 2006

Overall Project:

Black River Middle School

  • Continue installation of HVAC ductwork- vocal and new science room
  • Continue interior finishes (floor tile, painting, ceiling) renovation area
  • Continue interior electrical – lighting fixtures, fire alarm and outlets
  • Commence installation of building addition steel
  • Commence installation of new HVAC unit for Media Center
  • Commence installation of cabinets

Bragg Elementary School

  • Continue interior electrical – Renovation area’s
  • Continue interior painting, ceiling (Media/Computer lab/Teachers lounge)
  • Continue relocation of building electrical service
  • Continue installation of plumbing sinks (Teachers lounge)
  • Commence new addition building foundation layout and installation
  • Commence HVAC ductwork for Faculty Room

 

 

 

Dickerson Elementary School

  • Continue site-work for addition (gym) and drainage field
  • Continue interior painting (Nurse’s office)
  • Continue building footing installation for K addition
  • Commence installation of bathroom fixtures (Nurse’s and hallway bathrooms)
  • Continue gas line relocation to generator
  • Continue HVAC ductwork for Main office and Nurse’s office
  • Continue relocation of building generator and fuel supply
  • Continue interior / exterior electrical
  • Commence floor tile installation prep (Nurse’s office)

 

Impact to Students & Staff:

 

Noise:

 

  • Truck traffic and large machinery on site loading and unloading

 

Traffic and Parking:

    • Construction contractor parking is designated to the front & rear parking, not near pool parking ( Black River).
    • Bragg and Dickerson parking lots are closed for public use, due to extensive site construction

Cleanup:

  • Contractors were told to pick up any debris in the area.
  • Roadways will have to be kept clean in front of school and nearby roads.

 

Dickerson Elementary School – K-Wing foundation installation

 

 

Dickerson Elementary School – Gym building pad installation

 

Dickerson Elementary School – K-Wing foundation wall

 

 

 

 

 

Bragg Elementary School – Site electrical conduits

 

 

Bragg Elementary School – Teacher’s Lounge floor tile

 

Bragg Elementary School – Computer Lab