9/09/2006
Chester Township Public Schools
Black River – Bragg - Dickerson
Weekly Update
Activities of the last week:
Black River Middle School
- Continued light fixture installation – renovation area’s
- Completed interior wall framing ( vocal and science room)
- Continued interior painting, ceiling installation (Science wing)
- Continued HVAC ductwork installation (media, science and vocal)
- Commenced HVAC unit installation – Media Center
- Continued Carpet / floor tile installation
- Completed cabinet installation (6 th Science, vocal, renovations)
Bragg Elementary School
- Continued exterior site work for building addition
- Completed plumbing fixture installation – Teacher Lounge, Media Center
- Continued interior wall framing and ceiling grid – Media Center and Computer Lab
- Continued rough / finish interior-exterior electric
- Continued light fixture installation – Teacher Lounge
- Continued interior painting (Teacher lounge / Computer Lab / Media Center)
- Completed floor tile installation (Teacher Lounge, Computer Lab)
Dickerson Elementary School
- Continued rough interior / exterior electric
- Continued relocation of building electrical service
- Completed plumbing fixtures – Nurses lounge
- Commenced relocation of generator gas line
- Completed ceiling / floor tile installation – Nurses Area
- Continued site-work for addition building pad (gym) and drainage field
- Continued installation of footing for K addition
Scheduled Activities for the week of September 05– September 08, 2006
Overall Project:
Black River Middle School
- Continue installation of HVAC ductwork- vocal and new science room
- Continue interior finishes (floor tile, painting, ceiling) renovation area
- Continue interior electrical – lighting fixtures, fire alarm and outlets
- Commence installation of building addition steel
- Continue installation of new HVAC unit for Media Center
- Commence installation of interior door – Renovation area’s
- Continue plumbing installation – 6 th grade science, vocal
- Complete township inspections
Bragg Elementary School
- Continue interior electrical – Renovation area’s
- Continue interior painting, ceiling (Media/Computer lab/Teachers lounge)
- Continue relocation of building electrical service
- Commence new addition building foundation layout and installation
- Continue installation HVAC for Faculty Room
- Complete township inspections
Dickerson Elementary School
- Continue site-work for parking, roadway and drainage field
- Continue building footing installation for K addition
- Continue interior / exterior electrical
- Commence foundation layout and installation for Gym
- Complete township inspections
Impact to Students & Staff:
Noise:
- Truck traffic and large machinery on site loading and unloading
Traffic and Parking:
- Construction contractor parking is designated to the front & rear parking, not near pool parking ( Black River).
- Bragg and Dickerson parking lots are closed for public use, due to extensive site construction
Cleanup:
- Contractors were told to pick up any debris in the area.
- Roadways will have to be kept clean in front of school and nearby roads.

Dickerson Elementary School – Nurse’s suite

Dickerson Elementary School – Nurse’s suite

Black River Middle School – Addition building pad

Black River Middle School – HVAC unit installation Media center

Black River Middle School – Renovated science room

Black River Middle School – New 6 th grade science room

Black River Middle School – Media corridor