Activities of the last week:
Black River Middle School

  • Completed new 6th Grade Science room
  • Completed renovation of (2) science rooms and (2) classrooms
  • Commenced erection of new addition building steel
  • Continued construction of vocal room, computer lab and teachers lounge
  • Continued HVAC unit installation – Media Center
  • Continued interior finishes – ceiling, painting, and floor finishes
  • Completed township inspections

Bragg Elementary School  

  • Continued exterior site work for building addition
  • Completed renovation of teachers lounge
  • Continued interior electrical  – Media Center and Computer Lab
  • Continued rough / finish interior-exterior electric
  • Commenced new addition foundation layout
  • Completed township inspections

Dickerson Elementary School

  • Continued rough interior / exterior electric
  • Continued relocation of building electrical service
  • Completed  Nurse’s suite renovations
  • Completed relocation of generator gas line
  • Continued site-work for addition building pad (gym) and drainage field
  • Continued installation of footing for K addition
  • Commence installation of new gym foundations

 
Scheduled Activities for the week of September 11– September 15, 2006
Overall Project:
Black River Middle School

  • Continue interior finishes for vocal, computer lab, teachers lounge
  • Continue interior finishes (floor tile, painting, ceiling) renovation area
  • Continue new addition building steel installation
  • Commence installation of building addition steel
  • Continue interior renovation for Media Center
  • Continue underground plumbing for new addition

Bragg Elementary School

  • Continue interior electrical / lighting – Media / Computer Lab
  • Continue interior painting, ceiling (Media/Computer lab)
  • Continue relocation of building electrical service
  • Continue new addition building foundation layout and installation
  • Continue site work

Dickerson Elementary School

  • Continue site-work for parking, roadway and drainage field
  • Continue building footing installation for K addition
  • Continue interior / exterior electrical
  • Continue foundation layout and installation for Gym

Impact to Students & Staff:

Noise: 

  • Truck traffic and large machinery on site loading and unloading

Traffic and Parking:

    • Construction contractor parking is designated to the rear parking, not near pool parking (Black River).
    • Bragg and Dickerson parking lots have limited parking and revised traffic patterns, due to extensive site construction.
    • Construction traffic and deliveries will be limited during morning drop-off and afternoon pick-up.

Cleanup:

  • Contractors were told to pick up any debris in the area.
  • Roadways will have to be kept clean in front of school and nearby roads.

                                          

Black River Middle School – New addition steel erection

 

 


Black River Middle School – New addition steel

 


Black River Middle School – Renovated science classroom

 


Black River Middle School – Renovated classroom RM#11

 


Dickerson Elementary School – “K” foundation installation

 


Dickerson Elementary School – “K” addition foundation


Dickerson Elementary School – Gym foundation installation